Please be advised that beginning the week of October 7, 2024, GIP Paving Limited will begin work on road improvements in Bowmanville and Newcastle.
Roadwork will include the removal and replacement of applicable surface and base asphalt and concrete sidewalks and curbs, as well as asphalt paving, traffic line painting, driveway and roadway shoulder re-instatement (where applicable), ditching and associated restoration works.
These roadwork improvements will take place in the following locations:
Map of Clarington showing the affected areas. Red indicates roads receiving pavement rehabilitation and blue indicates roads receiving surface asphalt treatment.
Each road will be subject to lane reductions and short-term closures during working hours, and traffic may experience delays. The contractor will ensure that garbage and recycling pick-up and deliveries remain uninterrupted. Although construction will be disruptive at times, we appreciate your patience as crews complete the work.
Rural locations are anticipated to be completed by the end of November 2024, with the remaining locations completed by end of July 2025. Please note that timelines are approximate and will vary dependent on weather and other factors.
Matthew Mageau, Project Manager
905-809-4436
Ross Urbankiewicz, Superintendent
705-340-0742
We apologize for any inconvenience during construction and thank you for your patience.